Work described
From the filingFOR THE COMPLETE DEMOLITION OF THE EXISTING THREE (3) STORY MASONRY STRUCTURE. ALL PERMITTED DEMOLITION ACTIVITY TO BE DONE IN ACCORDANCE WITH SITE SAFETY DEMOLITION PLAN AND SUCH PLAN TO BE MAINTAINED ON SITE AT ALL TIMES. DEMOLITION TO BE DONE BY HAND AND WITH HAND TOOLS ONLY. PROTECTION OF PEDESTRIANS, PUBLIC RIGHT-OF-WAY, AND ADJACENT PROPERTIES TO BE IN PLACE PRIOR TO START OF WORK. SEPARATE STREETS DEPARTMENT APPROVAL REQUIRED FOR RIGHT-OF-WAY ENCROACHMENT OR CLOSURE.