Work described
From the filingReplace main electrical panel and transfer switch. Add new panel, breakers and interlock switch. Your application for a Building Permit has been reviewed for compliance with the 2022 State of Connecticut Building Code. The permit for the proposed work is approved. All work is subjected to field inspections. Comments below are to be reviewed and followed. 1. C/O detection per IRC 315.2.2 2.Any and all electrical work is to follow all applicable sections of the 2022 State of Connecticut Building and 2020 NFPA 70 National Electrical Code.