Work described
From the filingFirewood Kiln Your application for a Building Permit has been reviewed for compliance with the 2022 State of Connecticut Building Code. The permit for the proposed work is approved. All work is subjected to field inspections. Comments below are to be reviewed and followed. 1. Third party inspection may be required dependent on inspection results. IBC 1702.1 2. Propane tanks shall be installed per NFPA 58 3. Separation distances shall be maintained from other buildings/combustibles etc. 4. Concrete pad will be a minimum of 8" thick per our conversation.